Staging of material

A lot of paver jobs will vary depending on access, site conditions, project size and of course, the weather. These scenarios can have a total influence on your task from a timing stand point. Mindful factor to consider needs to be required to identify the time to start the paver installation. Always try to prevent any traffic or reduce on the prepared areas.

The supervisor or job manager should constantly have the products (sand/ pavers) distributed around the project website for simple and efficient installations. Paver pallets/bundles should be positioned in a way not to disrupt the paver installation. The proper pallet/bundle placement can make the actual job installation easier and quicker by lowering the general labor of managing the material.

Brick paver patterns

Pavers can be positioned in many different patterns depending upon their shape. Each paver shape will generally have a number of various hatch patterns that are offered by the maker.

Specialists need to take into consideration the traffic weight loads on their paver jobs. In most applications worldwide, it has actually been revealed that pavers laid in a herringbone pattern have performed sufficiently.

Pavers that are 60 mm (2 - 3/8 in) density are suitable for pedestrian applications. Pavers that are going to be used in industrial or industrial applications must be 80 mm (3 - 1/8 in) in density.

Reference/starting point for brick paver installation

There are a number of conditions that determine the starting point of a paver job.

When beginning to install pavers it is best to snap a true straight chalk line on the surface of the bedding sand or pull a real straight string line above the surface area of the bed linen sand at the finished elevation of the pavers This will help as a guide for preserving straight joint lines and will also enable the installer to make changes in the alignment of the pavers.

Structures and concrete suppressing are generally not straight and should not be used for developing straight joint lines. The use of string lines is vital to figure out the real straightness of the edge. As the paver installation advances, the string lines will help minimize the need for small trim pieces.

Joint width between pavers must be in between 1/16 and 3/16 in (2 and 5 mm ). There are some pavers with spacer bars on their sides. These will preserve a minimum joint width and enable the bed linen and jointing sand to get in in between each paver. Pavers with spacer bars are generally not laid in snug against each other considering that a string line will provide consistent joint spacing.

Installation of brick pavers.

Among the most extensively utilized approaches for the installation of pavers is hand installation of each paver. It is best to set up a single row of pavers along among the true straight lines that you have actually pulled or above the bed linen sand. This will give you a straight and true line off which to work. Once this row is established, you can continue to work outward into the field with the rest of the pavers. Always make sure to periodically inspect your joint lines to make sure they are straight and true. If not, modifications to the pavers can be made as you continue installing. Pavers ought to be installed hand tight. The very best approach is to position a paver versus another one and let it move down into the bed linen sand. Do not kick or tap the pavers into location as this can toss your lines out of real straightness.

When setting up pavers on a high grade, they need to be set up at the base of the grade going uphill. This will avoid the pavers from sneaking as they are being laid.

On big industrial and commercial applications, hand laying pavers would not be cost effective due to the labor intensity. The best way for installing pavers on large projects is to install them mechanically. The use of a mechanical laying device can install roughly 6000 - 7000 sq ft a day. There are a couple items a professional ought to consider before installing pavers mechanically:

1.) Mechanical installers are only capable of setting up pavers in particular patterns.

2.) The specialist should ensure that the manufacturer is capable of manufacturing and bundling pavers in the wanted pattern on the pallets for simple mechanical installation.

3.) Specialists might experience a color blending situation coming off the bundles of pavers Poor color blending might lead to an irregular looking installation. Many producers are consistent with color mixing on each package of pavers, however it is the professional's responsibility to ensure proper mixing in the field.

Cutting procedures for brick pavers.

Specialists normally have 2 methods of cutting pavers. When cutting pavers damp, it will assist lessen dust and will extend the diamond blades life. The operator of the brick saw ought to always cut the pavers away from the surface area of the paver field when cutting wet, due to the truth that the pavers will create a slurry that will stain the paver surface.

The brick saw operator should constantly use the appropriate security that is needed for operating a saw, such as eye, ear, respiratory and hand defense ).

Edging types

Edge restraints play a significant function in the general success of an interlocking pavement installation Edging restraints eliminate lateral movement of the pavers and hold the pavers securely together. Specifically at the external perimeter of the paver application, without an edging restraint, your project is ensured to stop working gradually.

There are a number of different edging restraints from South Florida Pavers which contractors can pick. Normally produced edge restraints are the most typically used by contractors. Made edging restraints can vary from, plastic edging, steel and aluminum, timbers or precast concrete and stone. An edging type that is utilized primarily in commercial and business applications is poured-in-place concrete curbs. This edging restraint is normally set up by other contractors.

Edging installation.

This could result in the migration of the bedding sand and ultimate lateral movement of the pavers. If there is a possibility of losing bed linen sand between the pavers and the edge restraint, then geo textile material is suggested. When a space between the pavers and the edging exceeds 3/8" (10mm), then the area should be filled with cut pavers.

Compaction of brick pavers.

After installation, the pavers have to be compacted. The whole area that is to be compressed ought to be swept tidy of any foreign things and particles that can cause scuffing or scratching on the surface of the pavers.

It is essential to have a compactor that can apply between 3000lbs. And 5000 lbs. Of centrifugal compaction force. In addition, it is necessary that the first compaction happens before any jointing sand has actually been applied to the pavers. If jointing sand is applied to the pavers before compaction takes place, this can trigger a bridging problem and will not permit the joints to be completely filled with jointing sand. This can likewise prevent the pavers from being effectively set into the bedding sand.

When compacting the pavers, it is suggested that you make a minimum of two passes in various instructions across the pavers. This will permit the pavers to be properly embeded in the bedding sand and will force the bedding sand up into the joints from the bottom of the pavers.

The compaction of the pavers is really critical to the last efficiency of the pavers. Failure to do proper compaction can lead to contortions and pavement failure in time.


Paver pallets/bundles need to be placed in a manner not to interfere with the paver installation. One of the most extensively used techniques for the installation of pavers is hand installation of each paver. The operator of the brick saw need to always cut the pavers away from the surface of the paver field when cutting damp, due to the fact that the pavers will produce a slurry that will stain the paver surface area. Edging restraints eliminate lateral movement of the pavers and hold the pavers firmly together. When a space in between the pavers and the edging exceeds 3/8" (10mm), then the space should be filled with cut pavers.